Phase one of the $12.14 million project is complete — nearly four times the size of the old building, built without a municipal property tax
DEWEY BEACH — Dewey Beach has officially opened its new town hall and police department, a three-story building on Coastal Highway that completes the first phase of a $12.14 million project.
The new municipal building at 1505 Coastal Highway is nearly four times the size of the old town hall, the Cape Gazette reports. It brings expanded town offices, a public meeting room, upgraded police dispatch, holding cells and improved security under one roof.

Costello Construction, the project's builder, says the completed first phase is a 25,000-square-foot facility with administrative offices, a modern dispatch center, secure holding cells, an evidence room and dedicated EMS areas.
Town hall administrative services moved to 1505 Coastal Highway starting Monday, Nov. 2, and the police department has relocated there as well, with all police and communication operations running from the new station. The town invited the public in for a community open house on Saturday, Nov. 7.

PHASE TWO IS UNDERWAY
The project is not finished. Phase two is underway: the old town hall is being demolished, and new EMS quarters and a police sally port will be built, the Cape Gazette reports.
The entire project is being completed without a municipal property tax.

HOW THE PROJECT GOT HERE
The town began discussing a new town hall and police station in January 2022, according to the town's project page. Commissioners approved an architectural design in May 2022 for a building at 1505 Coastal Highway — the site of the former Parking Enforcement office — to house the town administrative team, the police department, Parking Enforcement, Alderman Court and Sussex County EMS. The building was designed as a Risk Level 4 structure, the designation for essential facilities that must remain operational during and after major disasters.
The town council approved Costello Construction to build the project in February 2025. The former Parking Enforcement building on the site was demolished in March 2025, Sussex County increased its contribution to $1.5 million that same month, and the town held its groundbreaking ceremony in April 2025.

Sources: Cape Gazette, Nov. 13, 2026 (Ellen McIntyre); Town of Dewey Beach project page and community open house notice; Costello Construction project page.